• The 170 km² 3D seismic programme over the Mankota/Grasslands area (HEVI WI: 49%) has now been completed. Processing and interpretation are expected in early June and will enable the company to define and rank drilling locations.
• At least three wells are planned for 4Q26, with new production to be tied into the existing Soda Lake facility in 1H27. At helium prices of US$450–750/mcf at the plant gate, HEVI estimates that the existing 12 mmcf/d raw‑gas facility would deliver approximately US$7– ....
23 Apr 2026
Helium Evolution Inc. (HEVI CN): 3D Seismic acquisition completed. Drilling to start in 4Q26
Sign up to access
Get access to our full offering from over 100 providers
Get access to our full offering from over 100 providers
Helium Evolution Inc. (HEVI CN): 3D Seismic acquisition completed. Drilling to start in 4Q26
Helium Evolution Incorporated (HEVI:TSX) | 0 0 0.0%
- Published:
23 Apr 2026 -
Author:
Stephane Foucaud -
Pages:
5 -
• The 170 km² 3D seismic programme over the Mankota/Grasslands area (HEVI WI: 49%) has now been completed. Processing and interpretation are expected in early June and will enable the company to define and rank drilling locations.
• At least three wells are planned for 4Q26, with new production to be tied into the existing Soda Lake facility in 1H27. At helium prices of US$450–750/mcf at the plant gate, HEVI estimates that the existing 12 mmcf/d raw‑gas facility would deliver approximately US$7– ....